Phased Roadmap

AttributeValue
ProjectOpen Projects Hub
Version1.4
StatusAccepted
OwnerProduct Owner

Table of Contents​

Planning Principles​

  • Separate scope definition from implementation design.
  • Use MoSCoW for prioritization and resolve conflicts through Tech Lead + Product Owner.
  • Keep MVP focused on core validated workflows before expansion.
  • Architecture-impacting decisions must reference ADRs in 03-architecture.

Status (2026-10-07): Phase -1, Phase 0, and the MVP feature work are built; production release and the Phase 1 SEO and E2E items remain. Story-level status lives in work-items/. Viewer accounts (original F-011) were replaced by account-free Client Review (ADR-020).

Phase Overview​

PhaseNameObjectiveStatusTarget WindowExecution Mode
Phase -1UI/UX Prototyping & ValidationValidate UI designs and obtain stakeholder approval before developmentDoneWeek 0 (parallel)Parallel with Phase 0
Phase 0Foundation & Engineering ReadinessEstablish development infrastructure and standards before feature workDone (production deploy pipeline pending)Week 0 (parallel)Parallel with Phase -1
MVPCore Planning BackboneDeliver core planning value with secure access and exportsBuilt; release pendingWeeks 1-11Sequential
Phase 1UX and Entry-Flow HardeningImprove onboarding, entry flow, monetization config, and UI craftMostly built (SEO and E2E coverage open)Weeks 12-19Sequential
Phase 2Governance and Scale PreparationPrepare post-MVP governance, traceability depth, and scale planPlannedTBDSequential

Phase -1 (UI/UX Prototyping & Validation)​

Execution Model: Runs in parallel with Phase 0. Both phases must complete before MVP Week 1 begins.

Goals​

  1. Complete high-fidelity prototypes for all MVP features (F-001 through F-011).
  2. Validate UI/UX designs with Product Owner and key stakeholders.
  3. Establish visual design system (colors, typography, component patterns, spacing).
  4. Obtain formal stakeholder sign-off on all UI designs before engineering begins.
  5. Create design handoff artifacts and conduct walkthrough with Frontend Engineer.

Prioritized Tasks​

PriorityTaskOwnerEstimateDeliverable
MustComplete/update MVP screen prototypesUI/UX Designer3-4 days15-20 screens for F-001 to F-011
MustStakeholder walkthrough & feedbackProduct Owner1 dayConsolidated feedback document
MustIterate prototypes based on feedbackUI/UX Designer2-3 daysRevised prototypes addressing feedback
MustFinal approval gateProduct Owner0.5 daysSigned-off designs with approval artifact
MustDesign handoff documentationUI/UX Designer1-2 daysComponent specs, design tokens, assets
ShouldInteractive clickable prototypeUI/UX Designer2 daysFigma/Stitch clickable demo for user journeys
ShouldAccessibility review (WCAG 2.1 AA)UI/UX Designer1 dayAccessibility checklist and compliance notes
ShouldResponsive design variantsUI/UX Designer1-2 daysMobile/tablet breakpoint designs

Key Deliverables​

  • Complete prototype pack: All MVP screens designed and approved (15-20 screens)

    • Landing page and value proposition (F-006)
    • Authentication flows: login, signup, password reset (F-007, F-008, F-009)
    • Client and project management (F-001)
    • AI refinement workspace with provider selection (F-002)
    • Requirements backlog - Admin view with edit/approve controls (F-004)
    • Requirements backlog - Client Review view (read-only) (F-003, F-004)
    • Markdown export flow and confirmation (F-004)
    • AI credits management and API key configuration (F-010)
    • Client Review by project access code (F-011, ADR-020; replaces the Viewer invitation flow)
    • Minimal onboarding overlay for first-time Admin (F-005)
  • Visual design system documentation:

    • Color palette with WCAG 2.1 AA contrast ratios
    • Typography scale and font hierarchy
    • Component library specifications (buttons, forms, cards, tags, modals)
    • Spacing and grid system
    • Iconography guidelines
  • Design handoff package:

    • Component specifications (dimensions, states, behaviors, interactions)
    • Design token definitions (colors, typography, spacing values)
    • Asset export package (icons, logos, images, illustrations)
    • Interaction specifications (animations, transitions, micro-interactions)
    • Responsive breakpoints and layout guidelines
    • Ant Design component mapping and customization notes
  • Approval artifacts:

    • Stakeholder sign-off document with approval date
    • Consolidated feedback log with resolutions and deferral decisions
    • Deferred design improvements documented for Phase 1/2

Acceptance Criteria​

  • All MVP features (F-001 through F-011) have high-fidelity prototypes completed.
  • Prototypes validated with at least 2 stakeholders (Product Owner + 1 other).
  • All critical feedback incorporated or explicitly logged as deferred with rationale.
  • Product Owner formal sign-off obtained and documented.
  • Design handoff documentation complete and reviewed by Tech Lead and Frontend Engineer.
  • UI/UX Designer conducted walkthrough session with Frontend Engineer (Q&A completed).
  • Accessibility baseline (WCAG 2.1 AA) validated for all critical user flows.
  • Responsive design variants documented for mobile and tablet breakpoints.
  • Design system tokens ready for implementation (colors, typography, spacing).

Dependencies and Blockers​

Blocks:

  • Frontend UI implementation (cannot start building screens without approved designs)
  • Frontend component library setup (needs design tokens and component specifications)

Requires:

  • Requirements v1.6 complete (F-001 through F-011) ✅ Complete
  • User personas documented ✅ Exists in docs/00-context/user-personas.md
  • Existing prototypes in docs/05-prototype/ ✅ 15+ screens already created

Can Run in Parallel With:

  • Phase 0 Foundation & Engineering Readiness (backend setup, database, CI/CD, standards docs)

Coordination Points:

  • Day 5-7: Frontend Engineer available for design handoff review
  • Day 7: Joint readiness gate with Phase 0 before MVP starts

Phase 0 (Foundation & Engineering Readiness)​

Execution Model: Runs in parallel with Phase -1. Both phases must complete before MVP Week 1 begins.

Goals​

  1. Establish complete development environment with < 30 min setup time for new engineers.
  2. Configure all linting, formatting, and CI/CD quality gates.
  3. Define and document project structure and coding standards.
  4. Implement database foundation with schema, migrations, and seed data.
  5. Create API baseline with authentication middleware and health checks.
  6. Enable all engineers to start MVP feature work with clear conventions.

Prioritized Tasks​

PriorityTaskOwnerEstimateDeliverable
MustRepository structure & tooling configTech Lead1 dayMonorepo structure, linter configs, pre-commit hooks
MustDevelopment environment setup guideTech Lead2 daysdocs/development/SETUP.md
MustProject structure standardsTech Lead1 daydocs/development/PROJECT_STRUCTURE.md
MustCI/CD pipeline implementationBackend Engineer2-3 daysGitHub Actions workflows for backend + frontend
MustDatabase foundationBackend Engineer2 daysSchema, Alembic migrations, seed data scripts
MustAPI contract & auth middleware baselineBackend Engineer2 daysFastAPI baseline, JWT auth, health endpoints
MustCoding standards (essential)Tech Lead1 daydocs/development/CODING_STANDARDS.md
MustTesting standards (essential)Tech Lead1 daydocs/development/TESTING_STANDARDS.md
MustCode review guidelinesTech Lead0.5 daysdocs/development/CODE_REVIEW.md

Key Deliverables​

  • Monorepo structure: Backend and frontend folders with Clean Architecture and feature-based organization.
  • Development environment guide: Complete setup documentation enabling < 30 minute onboarding.
  • CI/CD pipelines: Automated quality gates (lint, type-check, test) for backend and frontend.
  • Database foundation: PostgreSQL schema, migration framework (Alembic), and seed data for local development.
  • API baseline: FastAPI application with versioning (/api/v1/), JWT authentication, CORS, error handling, and health checks.
  • Engineering standards: Essential coding standards, testing patterns, and code review guidelines.
  • Tooling configuration: Black, Ruff, mypy (backend); ESLint, Prettier, TypeScript strict (frontend).

Acceptance Criteria​

  • All engineers can clone repo and run full stack locally within 30 minutes.
  • Backend CI pipeline operational and passing (lint, type-check, test).
  • Frontend CI pipeline operational and passing (lint, type-check, test).
  • Database migrations execute successfully; seed data loads without errors.
  • Health check endpoints (/health, /ready) respond with 200 status.
  • OpenAPI documentation endpoint (/docs) accessible and functional.
  • All Phase 0 documentation reviewed and approved by engineering team.
  • Branch protection rules active on main branch (require CI pass + 1 approval).
  • At least one practice PR created, reviewed, and merged using new standards.

Dependencies and Blockers​

Blocks:

  • All MVP phase features (F-001 through F-011) - cannot start feature implementation without foundation.

Requires:

  • Supabase project created and configured.
  • GitHub repository initialized with appropriate permissions.
  • GitHub Actions enabled for CI/CD workflows.
  • Team access to development tools (Python 3.12+, Node.js 18+, Docker).

Can Run in Parallel With:

  • Phase -1 UI/UX Prototyping & Validation (no dependencies between backend setup and UI design)

Coordination Points:

  • Day 5-7: Frontend Engineer transitions from tooling setup to design handoff review with UI/UX Designer
  • Day 7: Joint readiness gate - both Phase -1 and Phase 0 must be complete before MVP starts

MVP Phase​

Goals​

  1. Deliver the core planning workflow with feature coverage for F-001 to F-004.
  2. Validate secure access and essential auth entry flows (F-007, F-009).
  3. Support Client Review (F-011): a client opens one project's approved stories with its access code (ADR-020).
  4. Ensure Must-priority quality baselines are mapped and owned.
  5. Run AI refinement on a platform-provided provider key; credit accounting and user-managed keys (F-010) are deferred to Phase 1.

Capacity Basis​

MVP scope is sized against an explicit assumption so that NFR-X08 is checkable rather than aspirational: 2 developers at ~12 story points per developer per week. Phase -1 and Phase 0 are complete, so EPIC-0's 64 points are already delivered and excluded.

MeasureValue
MVP-1 total314 points across 66 stories
Already delivered (EPIC-0)64 points
Remaining MVP work250 points
Assumed velocity~24 points per week
Implied duration~10-11 weeks (2.5 months)

This exceeds the original 1–1.5 month target even after deferring F-010, the Viewer management tail, validation testing, and all Phase 1 scope. NFR-X08 has been updated to match the scope the plan can actually deliver. Shortening it further means cutting from the core loop (lifecycle, refinement, approval, backlog, export, access), which would leave the MVP without a shippable end-to-end workflow. Re-derive these numbers if team size changes.

Prioritized Epics​

PriorityEpicLinked Feature(s)Linked RequirementsOwner
MustClient and project lifecycle governance (EPIC-1)F-001FR-001-01, FR-001-02, FR-001-03, FR-001-04, FR-001-05, FR-001-06, FR-001-07; NFR-001-01, NFR-001-02, NFR-001-03Product Owner
MustAI refinement and approval control (EPIC-3)F-002FR-002-01, FR-002-02, FR-002-03, FR-002-04, FR-002-05, FR-002-06; NFR-002-01, NFR-002-02, NFR-002-03Product Owner
MustAccess boundary and role enforcement (EPIC-4)F-003FR-003-01, FR-003-02, FR-003-03; NFR-003-01, NFR-003-02, NFR-003-03Tech Lead
MustBacklog and export deliverable (EPIC-5)F-004FR-004-01, FR-004-02, FR-004-03, FR-004-05; NFR-004-01, NFR-004-02Backend Engineer
MustAdmin authentication and recovery baseline (EPIC-2)F-007, F-009FR-007-01, FR-007-02, FR-007-03, FR-007-04, FR-007-05, FR-007-06, FR-007-07; FR-009-01, FR-009-02, FR-009-03, FR-009-04, FR-009-05, FR-009-06; NFR-007-01, NFR-007-02, NFR-007-03; NFR-009-01, NFR-009-02, NFR-009-03; NFR-003-04Tech Lead
MustClient Review by access code (replaces EPIC-7, ADR-020)F-011FR-011-01, FR-011-02, FR-011-03, FR-011-04, FR-011-05, FR-011-06, FR-011-09, FR-011-11, FR-011-12; NFR-011-01, NFR-011-02, NFR-011-03, NFR-011-04, NFR-011-05Tech Lead
MustCross-cut quality baseline (EPIC-9)F-001 to F-011NFR-X01, NFR-X02, NFR-X03, NFR-X08, NFR-X09, NFR-X10Tech Lead
MustCode quality tooling baseline (EPIC-12)F-001 to F-011NFR-X01, NFR-X03Tech Lead

Key Deliverables​

  • MVP scope baseline linked to feature-level requirements (F-001 to F-004, F-007, F-009, and the F-011 access slice).
  • Role-safe, approvable requirements backlog and Markdown export definition.
  • Client Review by project access code (no client accounts).
  • AI refinement running on a platform-provided provider key (credit accounting and user-managed keys deferred to Phase 1).
  • Security and privacy checklist for Must-priority workflows.
  • Automated code quality baseline (lint, format, type-check, pre-commit hooks, CI gates).
  • Traceability matrix generated from the work items in work-items/.

Acceptance Criteria​

  • All Must functional requirements in MVP scope are linked to an epic and owner.
  • All Must non-functional requirements are tied to measurable checks.
  • MVP excludes non-core collaboration expansion and non-essential integrations.
  • Remaining MVP effort stays within the capacity basis above, or the scope is re-cut.

Prerequisites​

Requires completion of:

  • Phase -1 (UI/UX Prototyping & Validation) - all designs approved and handed off ✅
  • Phase 0 (Foundation & Engineering Readiness) - infrastructure and standards complete ✅

Phase 1​

Goals​

  1. Improve first-use quality and public entry clarity (F-005, F-006, F-008).
  2. Strengthen readability, accessibility, and stakeholder transparency.
  3. Raise interface craft above component-library defaults and make public entry pages discoverable.

Prioritized Epics​

PriorityEpicLinked Feature(s)Linked RequirementsOwner
ShouldMinimal onboarding quality upliftF-005FR-005-01, NFR-005-01, NFR-005-02UI/UX Designer
ShouldLanding page messaging and conversionF-006FR-006-03, NFR-006-01, NFR-006-02Frontend Engineer
ShouldAccount creation flow maturityF-008FR-008-03, NFR-008-02Frontend Engineer
ShouldReadability and accessibility hardeningF-003, F-004, F-007FR-003-03, NFR-003-03, NFR-004-01, NFR-007-02, NFR-X07UI/UX Designer
ShouldSEO and discoverability (EPIC-10)F-006FR-006-01, FR-006-03, NFR-006-01, NFR-006-02, NFR-X11Frontend Engineer
ShouldUI craft and design quality (EPIC-11)F-001 to F-011NFR-X04, NFR-X07UI/UX Designer
MustAI credits and API key management (EPIC-6)F-010FR-010-01, FR-010-02, FR-010-03, FR-010-04, FR-010-05, FR-010-06, FR-010-07, FR-010-08, FR-010-09, FR-010-10, FR-010-11, FR-010-12; NFR-010-01, NFR-010-02, NFR-010-03, NFR-010-04, NFR-010-05, NFR-010-06Tech Lead
MustProvider selection and credit consumption (EPIC-3)F-002FR-002-07, FR-002-08Backend Engineer
ShouldExport scoping and empty-export guard (EPIC-5)F-004FR-004-04, FR-004-06Backend Engineer
ShouldViewer invitation management tail (EPIC-7) superseded by ADR-020F-011FR-011-07, FR-011-08, FR-011-10Backend Engineer
ShouldValidation testing and accessibility audit (EPIC-9)F-001 to F-011NFR-X03, NFR-X04, NFR-X05, NFR-X06, NFR-X07Tech Lead
ShouldArchitecture guards and dependency review (EPIC-12)F-001 to F-011NFR-X01, NFR-X03Tech Lead

Key Deliverables​

  • Improved onboarding and auth-adjacent user journey artifacts.
  • Accessibility and readability validation checklist per feature.
  • Updated feature traceability with Phase 1 story ownership.

Acceptance Criteria​

  • All Should requirements in Phase 1 have explicit quality targets and owners.
  • Client-facing outputs remain readable, non-technical, and read-only.

Phase 2 (Future)​

Goals​

  1. Formalize governance for backlog evolution and cross-phase traceability quality.
  2. Prepare scale-readiness and dependency governance without implementation commitments.

Prioritized Epics​

PriorityEpicLinked Feature(s)Linked RequirementsOwner
CouldCross-phase traceability governanceF-001 to F-011NFR-X03, NFR-X05, NFR-X06Tech Lead
CouldRisk and dependency governance modelF-001 to F-011NFR-X02, NFR-X08Tech Lead
CouldFuture collaboration policy framingF-003FR-003-02Product Owner

Key Deliverables​

  • Governance-ready traceability matrix maintenance policy.
  • Cross-phase risk and dependency register updates.
  • Prioritization rationale for post-MVP candidates.

Acceptance Criteria​

  • All Phase 2 entries are documented as candidates with dependency links.
  • No Phase 2 item introduces implementation design or tech-stack commitments.
  • Prioritization rationale is captured for each candidate epic.

Feature Traceability Matrix​

Feature IDFeature NamePhasePriorityLinked Epic(s)Linked Stories (US-*) — (M) MVP-1, (P1) Phase 1Status
F-001Client and Project Lifecycle ManagementMVP-1MustEPIC-1, EPIC-9US-EP1-BE-001 (M), US-EP1-BE-002 (M), US-EP1-BE-003 (M), US-EP1-BE-004 (M), US-EP1-FE-001 (M), US-EP1-FE-002 (M), US-EP1-REL-001 (M), US-EP1-UX-001 (M), US-EP9-BE-004 (M)Planned
F-002AI Refinement and Approval WorkflowMVP-1 + Phase 1MustEPIC-3, EPIC-11US-EP3-BE-001 (M), US-EP3-BE-002 (M), US-EP3-BE-003 (M), US-EP3-BE-004 (M), US-EP3-BE-005 (P1), US-EP3-FE-001 (M), US-EP3-FE-002 (M), US-EP3-REL-001 (M), US-EP3-UX-001 (M), US-EP11-FE-002 (P1), US-EP11-FE-005 (P1)Planned
F-003Access Control and Visibility BoundariesMVP-1 + Phase 1MustEPIC-2, EPIC-4, EPIC-9, EPIC-11US-EP2-BE-004 (M), US-EP4-BE-001 (M), US-EP4-FE-001 (M), US-EP4-REL-001 (M), US-EP4-UX-001 (M), US-EP9-BE-002 (M), US-EP11-FE-004 (P1)Planned
F-004Requirements Backlog and Markdown ExportMVP-1 + Phase 1MustEPIC-5, EPIC-11US-EP5-BE-001 (M), US-EP5-BE-002 (M), US-EP5-BE-003 (P1), US-EP5-FE-001 (M), US-EP5-FE-002 (M), US-EP5-REL-001 (M), US-EP5-UX-001 (M), US-EP11-FE-003 (P1)Planned
F-005Minimal OnboardingPhase 1ShouldEPIC-8US-EP8-BE-001 (P1), US-EP8-FE-001 (P1), US-EP8-REL-001 (P1), US-EP8-UX-001 (P1)Planned
F-006Landing Page ExperiencePhase 1MustEPIC-8, EPIC-10, EPIC-11US-EP8-FE-002 (P1), US-EP8-REL-002 (P1), US-EP8-UX-002 (P1), US-EP10-FE-001 (P1), US-EP10-FE-004 (P1), US-EP10-QA-001 (P1), US-EP11-FE-004 (P1)Planned
F-007Admin LoginMVP-1MustEPIC-2US-EP2-BE-001 (M), US-EP2-BE-003 (M), US-EP2-BE-004 (M), US-EP2-FE-001 (M), US-EP2-FE-003 (M), US-EP2-REL-001 (M)Planned
F-008Account CreationPhase 1ShouldEPIC-8US-EP8-BE-002 (P1), US-EP8-BE-003 (P1), US-EP8-FE-003 (P1), US-EP8-FE-004 (P1), US-EP8-REL-003 (P1), US-EP8-UX-003 (P1)Planned
F-009Reset PasswordMVP-1MustEPIC-2US-EP2-BE-002 (M), US-EP2-BE-005 (M), US-EP2-FE-002 (M), US-EP2-REL-002 (M)Planned
F-010AI Credits and API Key ManagementPhase 1MustEPIC-6US-EP6-BE-001 (P1), US-EP6-BE-002 (P1), US-EP6-BE-003 (P1), US-EP6-BE-004 (P1), US-EP6-BE-005 (P1), US-EP6-FE-001 (P1), US-EP6-FE-002 (P1), US-EP6-REL-001 (P1), US-EP6-UX-001 (P1)Planned
F-011Client Review Access (superseded Viewer Account Management, ADR-020)MVP-1 + Phase 1MustEPIC-7 (superseded)US-EP7-BE-001 (M), US-EP7-BE-002 (M), US-EP7-BE-003 (P1), US-EP7-BE-004 (M), US-EP7-BE-005 (M), US-EP7-FE-001 (M), US-EP7-FE-002 (M), US-EP7-REL-001 (M), US-EP7-UX-001 (M)Planned
NFR-X01–X11Cross-Cutting Quality BaselineMVP-1 + Phase 1MustEPIC-9US-EP9-BE-001 (M), US-EP9-BE-002 (M), US-EP9-BE-003 (M), US-EP9-BE-004 (M), US-EP9-PO-001 (M), US-EP9-QA-001 (M), US-EP9-QA-002 (P1), US-EP9-QA-003 (P1), US-EP9-QA-004 (P1), US-EP9-UX-001 (P1)Planned
—Foundational Setup and DeploymentMVP-1MustEPIC-0US-EP0-BE-001 (M), US-EP0-BE-002 (M), US-EP0-BE-003 (M), US-EP0-BE-004 (M), US-EP0-BE-005 (M), US-EP0-BE-006 (M), US-EP0-FE-001 (M), US-EP0-SP-001 (M), US-EP0-SP-002 (M), US-EP0-SP-003 (M), US-EP0-SP-004 (M)Planned
NFR-X11SEO and DiscoverabilityPhase 1ShouldEPIC-10US-EP10-FE-001 (P1), US-EP10-FE-002 (P1), US-EP10-FE-003 (P1), US-EP10-FE-004 (P1), US-EP10-FE-005 (P1), US-EP10-QA-001 (P1)Planned
—UI Craft and Design QualityPhase 1ShouldEPIC-11US-EP11-FE-001 (P1), US-EP11-FE-002 (P1), US-EP11-FE-003 (P1), US-EP11-FE-004 (P1), US-EP11-FE-005 (P1), US-EP11-FE-006 (P1), US-EP11-FE-007 (P1), US-EP11-UX-001 (P1)Planned
NFR-X01, NFR-X03Code Quality and MaintainabilityMVP-1 + Phase 1MustEPIC-12US-EP12-BE-001 (M), US-EP12-BE-002 (M), US-EP12-BE-003 (M), US-EP12-BE-004 (P1), US-EP12-BE-005 (P1), US-EP12-FE-001 (M), US-EP12-QA-001 (M)Planned

Risks and Blockers​

Risk / BlockerPhase ImpactedProbabilityImpactMitigationOwner
Scope creep between core planning and auth UXMVP, Phase 1MediumHighStrict MoSCoW gating and feature-to-phase traceability checksProduct Owner
Ambiguity in requirement ID ownershipMVPMediumHighMaintain requirement-level ownership table in role mappingTech Lead
Entry-flow quality drops due to split prioritiesPhase 1MediumMediumShared UX+FE checkpoint before phase sign-offUI/UX Designer
API key management security complexityMVPMediumHighEnforce NFR-010-01, NFR-010-02, NFR-010-03, NFR-010-04 security baseline; security review mandatoryTech Lead
Email delivery reliability for invitationsMVPLowHighImplement NFR-X10 with retry logic; monitor delivery metricsTech Lead
Prototypes require major rework during validationPhase -1LowMediumEarly stakeholder involvement; iterate on feedback quickly; existing prototypes reduce riskUI/UX Designer
Phase -1 and Phase 0 not completing in syncWeek 0MediumHighDaily coordination; contingency buffer 2-3 days if needed; Frontend Engineer helps both tracksTech Lead

Source References​


Last Updated: 2026-10-07

Note (2026-10-02): Rows and phases above that mention Viewer invitation, acceptance, or project-level access grants describe the original F-011. ADR-020 replaced them with account-free Client Review through a project access code, so EPIC-7 is no longer planned.